Removal procedure拆卸程序
|
|
1. Preparation1. 准备工作
1 Drive the vehicle into the lift position, activate the parking brake, and put the vehicle power supply in the "OFF" state.将车辆驶入举升机举升位置,启用驻车制动,整车电源处于“OFF”状态。
2 Disconnect the negative terminal of the 12V battery.断开蓄电池负极。
3 Lift the vehicle.举升车辆。
|
|
|
2. Recycle refrigerant2. 回收制冷剂
|
|
|
3. Remove the left front wheel arch assembly3. 拆卸左前轮眉总成
|
|
|
4. Remove the left front wheel assembly4. 拆卸左前车轮总成
|
|
|
5. Remove the left front wheel fender assembly5. 拆卸左前轮挡泥板总成
|
|
|
6. Disassemble the air conditioning compressor assembly6. 拆卸空调压缩机总成
|
|
|
1 Remove the fixing bolts ①, ②, and ③, and disconnect the air-conditioning pipelines A and B from the air-conditioning compressor assembly.拆卸固定螺栓①、②、③,断开空调管路A、B与空调压缩机总成的连接。
|
|
Recommended tools: 10mm socket推荐工具:10mm套筒 |
|
|
Caution:注意: |
|
♦
|
After disconnecting the air conditioning pipeline, seal or block the pipeline interface in time to prevent foreign matter from entering.断开空调管路后应及时密封或堵塞管路接口,避免异物进入。 |
|
|
|
|
|
2 Disconnect connectors A and B, remove 4 fixing bolts ①, and remove the air conditioning compressor assembly.断开接插件A、B,拆卸4颗固定螺栓①,取下空调压缩机总成。
|
|
Recommended tools: 10mm socket推荐工具:10mm套筒 |
|
|
Warning:警告: |
|
♦
|
Be careful when removing the air conditioner compressor assembly to avoid component damage or even personal injury caused by falling or bumping.取下空调压缩机总成时应谨慎操作,避免因掉落或磕碰造成部件损坏甚至人员受伤。 |
|
|
|
Installation procedure安装程序
|
|
1. Install air conditioning compressor assembly1. 安装空调压缩机总成
|
|
|
1 Place and adjust the air conditioning compressor assembly to the installation position, install and tighten 4 fixing bolts ①, and connect connectors A and B.放置并调整空调压缩机总成到安装位置,安装4颗固定螺栓①并紧固,连接接插件A、B。
|
|
Recommended tools: 10mm socket推荐工具:10mm套筒 |
|
|
Torque requirement: 22-28N·m扭矩要求:22-28N•m |
|
|
Warning:警告: |
|
♦
|
Care should be taken when installing the air conditioner compressor assembly to avoid component damage or even personal injury caused by falling or bumping.安装空调压缩机总成时应谨慎操作,避免因掉落或磕碰造成部件损坏甚至人员受伤。 |
|
|
|
|
|
2 Connect the air conditioning pipelines A and B to the air conditioning compressor assembly, install and tighten the fixing bolts ③, ②, ①.连接空调管路A、B到空调压缩机总成,安装固定螺栓③、②、①并紧固。
|
|
Recommended tools: 10mm socket推荐工具:10mm套筒 |
|
|
Torque requirement: 6-10N·m扭矩要求:6-10N•m |
|
|
Caution:注意: |
|
♦
|
The O-ring of the air conditioning pipeline is a disposable part, please use new parts for each installation.空调管路O型圈为一次性部件,每次安装请使用新件。 |
|
|
|
|
|
2. Install the left front wheel fender assembly2. 安装左前轮挡泥板总成
|
|
|
3. Install the left front wheel arch trim assembly3. 安装左前轮眉总成
|
|
|
4. Install the left front wheel assembly4. 安装左前车轮总成
|
|
|
5. Add refrigerant5. 加注制冷剂
|
|
|
6. Land the vehicle, connect the negative terminal of the 12V battery, start the vehicle, and check that the air conditioning and refrigeration system should be working normally.6. 降落车辆,连接蓄电池负极,启动车辆,检查空调制冷系统应正常工作
|