EV systems › High-voltage battery system › Repair
电池组箱总成(换电版) · T00618226

 Battery pack assembly (battery-swap version)电池组箱总成(换电版)

Removal procedure拆卸程序
1. Preparation1. 准备工作
1 Drive the vehicle into the lift position, activate the parking brake, and put the vehicle power supply in the "OFF" state.将车辆驶入举升机举升位置,启用驻车制动,整车电源处于“OFF”状态。
2 Disconnect the negative terminal of the 12V battery.断开蓄电池负极。
3 Lift the vehicle.举升车辆。
2. Remove the battery pack assembly2. 拆卸电池组箱总成
Graphic
1 Use a high-voltage battery lifting tool to lift the battery pack assembly until it is slightly stressed.使用动力电池举升工具顶起电池组箱总成至轻微受力。
Special tools: high-voltage battery lifting tool, high-voltage battery lifting tool-support beam专用工具:动力电池举升工具、动力电池举升工具-支撑横梁
  Note:提示:
♦  Correctly align the high-voltage battery lifting tool with the battery pack assembly, and avoid fixing bolts as much as possible to avoid restrictions on disassembly and assembly.将动力电池举升工具正确对准电池组箱总成,且尽可能避开固定螺栓,避免拆装受限。
Graphic
2 Loosen the 4 fixing bolts ①.拧松4颗固定螺栓①。
Recommended tools: 12-point 15mm socket推荐工具:十二角15mm套筒
  Note:提示:
♦  The figure shows disassembly on the right side as an example, and it needs to be done on both sides at the same time.图示以右侧拆卸为例,需在两侧同时操作。
Graphic
3 Slowly lower the high-voltage battery lifting tool and remove the battery pack assembly A.缓慢降落动力电池举升工具,取下电池组箱总成A。
Special tools: high-voltage battery lifting tool, high-voltage battery lifting tool-support beam专用工具:动力电池举升工具、动力电池举升工具-支撑横梁
Installation procedure安装程序
1. Install the battery pack assembly1. 安装电池组箱总成
Graphic
1 Place the battery pack assembly A on the high-voltage battery lifting tool, and slowly raise the high-voltage battery lifting tool.将电池组箱总成A放置到动力电池举升工具上,缓慢升起动力电池举升工具。
Special Tools: Power Battery Lifting Tool专用工具:动力电池举升工具
  Note:提示:
♦  Before lifting to the installation position, confirm that the high-voltage battery is aligned with the body positioning pins.举升到安装位置前,确认动力电池与车身定位销对准。
2 Raise the high-voltage battery lifting tool until the high-voltage battery fits the car body.升起动力电池举升工具直至动力电池与车身贴合。
Graphic
3 Install the 4 fixing bolts ① and tighten them.安装4颗固定螺栓①并紧固。
Recommended tools: 12-point 15mm socket推荐工具:十二角15mm套筒
Torque requirement: 68-82N·m扭矩要求:68-82N•m
  Note:提示:
♦  The figure shows installation on the right side as an example. Fixing bolts need to be installed on both sides at the same time.图示以右侧安装为例,需同时在两侧安装固定螺栓。
♦  Tighten the fixing bolts diagonally to the specified torque.对角紧固固定螺栓到规定扭矩。
Graphic
4 Lower the high-voltage battery lift tool and remove.降落动力电池举升工具并移出。
2. Connect the negative terminal of the 12V battery2. 连接蓄电池负极
3. Connect the diagnostic tool and perform reloading of the high-voltage battery system3. 连接诊断仪,执行动力电池系统重新加载
4. Land the vehicle, start the vehicle and drive off the lift, conduct road test and check4. 降落车辆,起动车辆并驶离举升机,路试检查